Project Update: March 3, 2024
Posted by Michael Allen on Mar. 3, 2024.
There has been a lot of progress made in the past few weeks. We are still on track to open the arena in around 2 weeks.
Project Update: February 18, 2024
Posted by Michael Allen on Feb. 18, 2024.
The building project continues to move along rapidly. We are on track to open the arena in around 1 month.
This week they finished polishing the concrete floor and stage. They have also made a lot of progress on installing drywall and painting.
Project Update: February 1, 2024
Posted by Michael Allen on Feb. 1, 2024.
There has been huge progress over the past 2 weeks. The drywall in the arena and backstage is complete. The ceiling has been painted and wall painting is going to start soon. They have also closed the large hole in the side of the building, and framing on that side is starting soon.